Today, January 3, at 02:50 am, unit №4 of Rivne NPP was disconnected due to defect of separator-superheater valve in accordance with the previously agreed bid.
The estimated date of repair completion is January 7, spokesperson of Rivne NPP Viktoria Leonova informed.
As at 8 am, January 3, two units of Rivne NPP operated with a total load of 1375 MW.