Hydraulic pressure tests of heating systems, started on April 23 of this year, are expected to be finished by September, press office of the Kyiv city state administration reports.

Thus, as of July 25, 2012, 936 failures were found and 724 of them were already fixed.

According to the report, the current test schedule was established taking into account the schedule of Euro 2012. During the championship, the tests were carried out exclusively in the residential districts of the capital.

As a reminder, the hydraulic testing of heating systems is a compulsory annual procedure, being performed in order to properly prepare the system for the next heating season.