The fourth generating set of the Rivne nuclear power plant resumed production of electricity at 2035 [1735 gmt] on 23 July following emergency repairs, the Ukrainian state nuclear regulator has said, RedNova reported .

The generating set was stopped automatically on 19 July due to a fault in the controls of the turbine department. On the morning of 24 July the generating set's output was brought up to 550 megawatt.

Eleven out of 15 generating sets are currently in operation at the Ukrainian nuclear power plants. Repairs continue at the second set of the Zaporozhye plant, the second and the fourth sets of the Rivno plant and the third set of the South-Ukrainian plant.